Back to Production
CC-J-26016
44 × C056 Alver
Workshop job
Details
- Status
- Upholstery
- Order
- CC-O-26016
- Finish
- Natural ash
- Work area
- Upholstery workshop
- Due date
- 29 Nov 2026
- Scheduled date
- 22 Nov 2026
- Allocated material
- Contract upholstery, charcoal
- Material requirement
- 52.8 m
- Allocation status
- 4 m on hand
- Specifications
- Approved
Production stages
Six workshop stages. Frame preparation issues the recorded allocated fabric; insufficient stock blocks the move.
Design approval
Materials allocated
Frame preparation
Upholstery
Finishing
Ready to dispatch
Notes
Illustrative fabric requirement: 1.2m per unit. Confirm actual cut plan.
Order context
Manly Function Rooms · Members lounge refurbishment
CC-O-26016