18 Nov 2026Demo
Back to Production
CC-J-26007

26 × C035 Kristy

Workshop job

Details

Status
Design approval
Finish
American oak
Work area
Upholstery workshop
Due date
20 Nov 2026
Scheduled date
22 Nov 2026
Allocated material
Contract upholstery, sand
Material requirement
31.2 m
Allocation status
190 m on hand
Specifications
Awaiting approval

Production stages

Six workshop stages. Frame preparation issues the recorded allocated fabric; insufficient stock blocks the move.

Design approval
Materials allocated
Frame preparation
Upholstery
Finishing
Ready to dispatch

Notes

Illustrative fabric requirement: 1.2m per unit. Confirm actual cut plan.

Order context

Riverbank RSL · Gaming lounge fitout

CC-O-26007